Construction 'No Damage for Delay' Clause Enforceability & Exceptions Analyzer
Analyze commercial and public works construction 'No Damage for Delay' (NDFD) exculpatory clauses, modeling statutory and case law exceptions across New York (Corinno Civetta 4-part rule), California (Pub. Cont. Code § 7102), Washington (RCW 4.24.360 void ban), Texas (Zachry active interference), and Florida.
Owner granted time, but denied all financial damages
Frequently Asked Questions
A 'No Damage for Delay' clause is an exculpatory contract provision stating that in the event of project delays caused by the owner or its agents, the contractor's sole and exclusive remedy shall be an extension of contract time, with no entitlement to monetary damages, extended overhead, equipment standby, or lost productivity.
In Corinno Civetta Construction Corp. v. City of New York (1986), the New York Court of Appeals held that NDFD clauses will NOT bar monetary recovery if the delay: (1) Was caused by the owner's bad faith or willful, malicious, or grossly negligent conduct; (2) Was uncontemplated (beyond the contemplation of the parties at contracting); (3) Was so unreasonable that it amounted to an intentional abandonment of the contract; or (4) Resulted from the owner's breach of a fundamental contractual obligation (e.g., providing defective plans).
In Washington State, RCW 4.24.360 declares all NDFD clauses in public and private construction contracts completely void against public policy. In California, Public Contract Code § 7102 prohibits public agencies from using NDFD clauses to bar damages for unreasonable delays not contemplated by the parties.