US Construction 'No Damage for Delay' (NDFD) Clause & Exceptions Analyzer

Analyze construction 'No Damage for Delay' (NDFD) clause enforceability across US states. Evaluates the 4 Corinno Civetta common law exceptions (active interference, uncontemplated delay, abandonment), Washington RCW 4.24.360 complete void ban, and California Public Contract Code § 7102.


Frequently Asked Questions

An NDFD clause is a contract provision stating that in the event of an owner-caused or unexpected project delay, the contractor's sole and exclusive remedy shall be an extension of contract time, completely waiving any right to recover monetary damages for extended general conditions, jobsite trailers, equipment idling, or home office overhead.

Under the seminal New York decision Corinno Civetta Construction Corp. v. City of New York (1986), an NDFD clause is unenforceable if the delay was: (1) caused by the owner's bad faith or active interference; (2) uncontemplated by the parties at the time of contracting; (3) so unreasonable that it constitutes an intentional abandonment of the contract; or (4) the result of the owner's gross negligence or willful misconduct.

Washington state has the strictest statute (RCW 4.24.360), which declares all NDFD clauses in both public and private construction contracts completely void against public policy. California Public Contract Code § 7102 voids NDFD clauses on public agency projects if the delay is unreasonable. Other states, like Colorado (C.R.S. § 24-91-103.5) and Ohio (ORC § 4113.62), also statutory bar NDFD provisions in public works.