Model strict statutory deadlines under 40 U.S.C. § 3133, verify second-tier 90-day preliminary notice rules, track 1-year lawsuit statutes of limitation, and draft formal surety claim notices.
Government sovereign immunity bars mechanics liens against federal and municipal properties. Payment bonds issued by corporate sureties under the Miller Act are the sole and exclusive remedy for unpaid subcontractors and suppliers.
Second-tier claimants (those lacking a direct contract with the prime contractor) MUST give written notice to the prime contractor within exactly 90 days after the date they last performed labor or supplied materials. Missing day 90 is fatal.
An action under the Miller Act must be filed in United States District Court no later than one (1) year after the date on which the claimant last performed labor or supplied material. Settlement negotiations do not toll this statute.