Legal & Contracts
US Construction Contractor Eichleay Formula Unabsorbed Overhead Calculator
Calculate unabsorbed home office overhead damages caused by owner-directed project suspensions or government delays using the federally recognized Eichleay Formula.
$
$
$
Executive salaries, accounting, HQ rent/utilities
Total calendar days including delay period
Compensable suspension / standby days
Allocable Overhead Ratio
20.0%
Allocable Contract Overhead
$360,000
Daily Overhead Rate
$1,000.00 / day
Total Eichleay Claim
$75,000
Frequently Asked Questions
The Eichleay Formula is the exclusive, federally approved method (established in Eichleay Corp., ASBCA No. 5183 (1960)) for calculating home office overhead damages that a contractor incurs when an owner or the federal government suspends or delays project work. It compensates the contractor for fixed home office costs (salaries, rent, utilities) that could not be absorbed by other revenue during the delay.
Yes. While the Eichleay formula originated in federal government contracting, appellate courts in many states (including California, Florida, Massachusetts, and Ohio) recognize and apply the Eichleay Formula to private commercial construction disputes, provided the contract does not contain an express 'No Damages for Delay' waiver.
The owner's most common defense is proving that the contractor was NOT truly on 'standby'. If the owner can show that the delay was scheduled with a fixed restart date, that the contractor demobilized its supervisory staff, or that the contractor successfully secured new replacement contracts during the suspension, the Eichleay claim will be barred.