Construction Subcontract Risk • State Public Policy

Pay-If-Paid vs Pay-When-Paid Auditor

Audit subcontract contingent payment clauses across all 50 US jurisdictions. Determine whether a "pay-if-paid" risk-shifting clause is strictly void as against public policy (e.g., California, New York) or fully enforceable as an express condition precedent (e.g., Texas, Florida).

Subcontract Terms & Project State

Enforceability Audit & Payment Recovery Status

CONDITION PRECEDENT ENFORCEABLE: Subcontractor cannot sue GC directly under Texas law.
Clause Classification Pay-If-Paid (Valid)
GC Payment Obligation Shielded by Condition
State Public Policy Stance: Enforceable (Texas Bus. & Com. § 56)
Mechanic's Lien Rights Status: 100% Preserved Against Property
Prevention Doctrine Exception: Not Asserted
Reasonable Time Limit (Pay-When-Paid): N/A (Pay-If-Paid Language)

Immediate Subcontractor Claim Value: $385,000 (Lien Only)
Litigation Strategy & Subcontractor Remedies:
Auditing contingent payment clauses...
Pay-If-Paid vs. Pay-When-Paid: The Core Legal Distinction
Pay-If-Paid (Condition Precedent):

Shifts the risk of owner non-payment completely to the subcontractor. If the owner never pays, the general contractor never owes the subcontractor a penny. In anti-pay-if-paid states (NY, CA, IL, NC), these clauses are struck down as illegal waivers of mechanic's liens.

Pay-When-Paid (Timing Mechanism):

Merely gives the GC a "reasonable time" to obtain funds from the owner before paying the sub. In all US jurisdictions, once a reasonable time has elapsed (typically 60 to 120 days), the GC MUST pay the sub from its own funds!

The Prevention Doctrine:

Even where pay-if-paid is legal, a general contractor CANNOT invoke the defense if the owner withheld payment because of the GC's own default, mismanagement, or delay under the common law Prevention Doctrine.