Hub Home C.R.S. § 38-22-109

Colorado Mechanics Lien Notice of Intent to File Auditor

Audit strict statutory timing under Colorado mechanics lien law. C.R.S. § 38-22-109(3) mandates that a Notice of Intent to File a Lien Statement must be served on the owner and principal contractor at least 10 days BEFORE recording the lien in county records.

Job Dates & Notice Milestones

Statutory deadline: File lien within 4 months of last work.
Must be served via certified mail / personal delivery ≥ 10 days before recording.
🏠 Home Hub