🔨

Colorado Mechanic's Lien Law (C.R.S. § 38-22-109) Notice of Intent & Deadlines Auditor

Audit Colorado mechanics lien perfection under C.R.S. § 38-22-101 et seq., tracking mandatory 10-day Notice of Intent to File Lien Statement (C.R.S. § 38-22-109(3)), 4-month recording deadline, and 6-month foreclosure suit limitation.

Construction & Real Estate Law US Statutory Standard
Colorado Lien Timing & Parties C.R.S. § 38-22-101 et seq.
Statutory Deadline Tracking
Input last work dates to audit Colorado mechanic's lien deadlines.
Colorado Statutory Mechanics (C.R.S. 38-22)
  • 10-Day Notice of Intent (§ 38-22-109(3)): Mandatory condition precedent; must be served on owner and principal contractor at least 10 days before recording the lien statement.
  • 4-Month Recording Rule (§ 38-22-109(5)): Lien statement must be recorded in the county clerk and recorder's office within 4 calendar months after last furnishing.
  • 6-Month Foreclosure Rule (§ 38-22-110): Foreclosure action and lis pendens must be commenced within 6 months after last work or completion.
🏠 Home Hub