Calculate Colorado mandatory 10-day Notice of Intent to File a Lien delivery timelines, 4-month recording windows for contractors, and the 6-month lawsuit limit under C.R.S. § 38-22-110.
This legal-grade auditing calculator analyzes critical statutory milestones, deadlines, and strict procedural requirements established by state and federal codes. Adherence to exact calendar calculation prevents catastrophic forfeiture of rights, civil penalties, or invalidation of legal instruments.
Under C.R.S. § 38-22-109(3), before recording a statement of lien, the claimant must serve a written Notice of Intent to File a Lien Statement on the property owner (or reputed owner) and the principal contractor at least 10 days before recording the lien in the county records. Failure to serve this notice voids the lien.
Under C.R.S. § 38-22-109(4) and (5), laborers claiming for day or piece labor must record within 2 months after completion of building work. All other contractors, subcontractors, and materialmen must record within 4 months after the day on which the last labor or materials were furnished.
Under C.R.S. § 38-22-110, an action to enforce the lien must be commenced in district court, and a notice of lis pendens recorded, within 6 calendar months after the last labor was performed or materials furnished, or 6 months after completion of the structure.