1. Prime Contract & Retainage Terms
Approved additions or deductions modifying the contract sum
2. Work Progress & Prior Payments
Suitably stored and insured materials not yet incorporated into the building
Understanding AIA G702 / G703 Construction Progress Billing
General contractors and construction managers use the American Institute of Architects (AIA) G702 Application and Certificate for Payment alongside the G703 Continuation Sheet as the universal standard for commercial construction billing:
- Line-by-Line Schedule of Values: Every trade subcontract allocates the total contract price into itemized work packages (framing, MEP rough-ins, drywall, finishes).
- Retainage Withholding: Typically 5% to 10% is deducted from all work completed and stored materials to create a financial performance cushion protecting the owner until substantial completion.
- Stored Materials Verification: Allows contractors to receive progress billing on custom manufactured structural steel or chillers stored securely in certified bonded warehouses prior to jobsite delivery.