PMI PMP / PMBOK Guide 7th Edition & Process Groups Time: 00:00

PMP: Project Procurement & Vendor Contract Management Practice Exam

Master PMI Project Management Professional (PMP) procurement domain concepts: Contract types (Firm Fixed Price FFP, Fixed Price Incentive Fee FPIF, Cost Plus Fixed Fee CPFF, Cost Plus Incentive Fee CPIF, Time and Materials T&M), target cost/fee formulas, Point of Total Assumption (PTA), source selection, and dispute claims resolution.

Question 1: Under a Fixed Price Incentive Fee (FPIF) contract, the target cost is $1,000,000, target fee is $100,000, ceiling price is $1,200,000, and the sharing ratio is 80% buyer / 20% seller. If the final actual cost delivered by the contractor is $1,100,000, what is the final total price paid to the seller?
Question 2: For the same FPIF contract (Target Cost = $1,000,000, Target Fee = $100,000, Ceiling Price = $1,200,000, Buyer/Seller share = 80/20), what is the Point of Total Assumption (PTA)?
Question 3: Which contract type places the HIGHEST cost and performance risk on the SELLER (vendor) and the LOWEST financial risk on the BUYER?
Question 4: When project scope is uncertain, evolving, or emergency labor augmentation is required for an unknown duration, which contract type is most appropriate, typically accompanied by a Not-to-Exceed (NTE) threshold?
Question 5: In project procurement management, what is the primary difference between a Request for Proposal (RFP) and a Request for Quote (RFQ)?
Question 6: During a multi-year civil infrastructure project subject to volatile commodity pricing (e.g., steel, diesel, asphalt), which contract type best protects both parties against macroeconomic volatility?
Question 7: Under a Cost Plus Incentive Fee (CPIF) contract, Target Cost is $500,000, Target Fee is $50,000, Min Fee is $20,000, Max Fee is $80,000, and sharing ratio is 70/30 (buyer/seller). If actual cost is $400,000, what is the final fee earned by the seller?
Question 8: What document provides potential sellers with a clear, concise, and complete description of the work to be performed, enabling them to evaluate their capability and submit realistic bids?
Question 9: When a buyer and seller cannot resolve a disputed change claim regarding cost or schedule adjustments during project execution, what is the preferred progression of Alternative Dispute Resolution (ADR)?
Question 10: What procurement activity must occur before formal procurement closeout is finalized and final payment is released to the seller?