PMP: Earned Value Management (EVM) & Forecasting Practice Exam

Master PMI Project Management Professional (PMP) Earned Value Management (EVM) formulas: Planned Value (PV), Earned Value (EV), Actual Cost (AC), Cost Variance (CV), Schedule Variance (SV), CPI, SPI, Estimate at Completion (EAC) under 4 forecasting methods, and To-Complete Performance Index (TCPI).

Question 1: A project has a Budget at Completion BAC = $500,000. At the current reporting milestone, Planned Value PV = $220,000, Earned Value EV = $200,000, and Actual Cost AC = $250,000. What are the Cost Variance (CV) and Schedule Variance (SV)?
Question 2: For the same project (EV = $200,000, AC = $250,000, PV = $220,000), what are the Cost Performance Index (CPI) and Schedule Performance Index (SPI)?
Question 3: If future remaining project work is expected to proceed at the CURRENT cost performance efficiency rate (CPI continues unchanged), what is the forecasted Estimate at Completion (EAC)?
Question 4: If the project's past cost variances were typical of initial startup anomalies and all FUTURE remaining work will be performed at the ORIGINAL budgeted rate (budgeted plan rate), what is the EAC?
Question 5: If BOTH cost and schedule performance factors (CPI and SPI) must be taken into account to forecast EAC because a firm project completion deadline must be met, what formula is applied?
Question 6: What is the To-Complete Performance Index based on the original budget (TCPI_BAC) for this project (BAC = $500,000, EV = $200,000, AC = $250,000)?
Question 7: What does a TCPI value GREATER than 1.0 (e.g., TCPI = 1.20) indicate to the project manager?
Question 8: What is the Variance at Completion (VAC) if the BAC is $500,000 and the approved revised EAC is $625,000?
Question 9: What is Earned Schedule (ES) in modern EVM extensions, and why was it developed to replace traditional SPI near project completion?
Question 10: In an Agile project tracking progress with EVM metrics, how is Earned Value (EV) typically quantified?