PE Civil Water Resources: Stormwater Detention Pond Routing Practice Exam

Master NCEES PE Civil Water Resources exam problems: Stormwater detention basin sizing, stage-storage-discharge curves, reservoir routing via Modified Puls level-pool method, orifice and sharp-crested weir hydraulics, sediment forebay volumes, and emergency spillway freeboard.

Question 1: A circular bottom orifice with diameter D = 1.5 ft discharges from a detention pond under an effective hydraulic head H = 9.0 ft above the orifice centroid. Assuming an orifice discharge coefficient Cd = 0.60, what is the discharge rate Q?
Question 2: For a rectangular sharp-crested emergency spillway weir with effective crest length L = 20.0 ft (suppressed without end contractions, Francis weir coefficient Cw = 3.33), what is the discharge Q when head over crest H = 2.5 ft?
Question 3: In hydrologic reservoir routing using the Modified Puls (Storage-Indication) method, what governing continuity equation forms the basis for routing the inflow hydrograph through the detention basin?
Question 4: When calculating the storage volume of a trapezoidal detention pond between two elevation contours A1 (at elevation 100 ft) and A2 (at elevation 105 ft), which formula yields the most accurate geometric volume?
Question 5: What is the primary design purpose of a sediment forebay located at the inflow point of an extended detention wet pond?
Question 6: A post-development watershed of 40 acres has a 10-year rational runoff coefficient C = 0.65 and rainfall intensity i = 4.2 in/hr. What is the peak inflow rate entering the detention facility?
Question 7: What condition describes 'submerged weir flow' over an internal riser structure in a detention pond, and how does it affect discharge?
Question 8: What minimum vertical freeboard is standardly required between the peak 100-year routed maximum water surface elevation (100-yr WSEL) and the top of the embankment crest for a detention dam per state dam safety / NRCS standards?
Question 9: In NRCS TR-55 unit hydrograph methodology, what parameter represents the time from the center of mass of excess rainfall to the peak rate of runoff (tp)?
Question 10: Why is an anti-seep collar or filter diaphragm installed around a low-level concrete outlet conduit penetrating through a compacted earthen detention pond embankment?